SlovSEFF III projects


Blue portfolio Industrial energy efficiency             
Green portfolio  Renewable energy            
Yellow portfolio Residential energy efficiency

 

 

SlovSEFF III achievements

EN 2018 07 28

 

PROJECT DESCRIPTION
SLOVSEFF LOAN (€) GHG SAVINGS (tCO2e/a) ENERGY SAVINGS (MWh/a) CARBON     REDUCTION       COMPENSATION (€)

FACT SHEET

Circuit THK and Šalgotarjánska

Replacement of old and poorly insulated heat distribution pipes in the “THK” and Šalgotarjánska” branches with new preinsulated pipes with lower heat loss.

588,041.16 117 1,061.00 29,402.06 download icon 1

Circuit Jahodníky

Installation of new CHEs and installation of new double pipe heat distribution system.

780,200.00 343 687.00 39,010.00 download icon 1

Circuit OST Centrum + Circuit Balkán + Circuit Namestie Slobody

Replacement of old and poorly insulated heat distribution pipes in “Balkán” and “OST Centrum” branches of CHS with new pre-insulated pipes with lower heat loss.
306,227.58  192 949.60  15,311.38 download icon 1

Circuit Kukučínova + Farkaška-Francisciho

Replacement of old, poorly insulated pipes of the “PK Farkaška” and “OST Kukučínova” circuits with new preinsulated pipes with lower heat loss.
242,206.67 104 521.50 12,110.33 download icon 1

South circuitKrupina

Replacement of old, poorly insulated heat distribution pipes of the south branch of the CHS with new preinsulated pipes with lower heat loss.
112,431.13 34 167.00 5,621.56 download icon 1

Circuit Venevská - Velký Krtíš

Boiler room reconstruction and replacement of old, poorly insulated heat distribution pipes of the CHS with new preinsulated pipes with lower heat loss.
258,297.76 92 662.00 12,914.89 download icon 1

Circuit Pliešovce

Replacement of old poorly insulated heat distribution pipes in the north branch of CHS with new preinsulated pipes with lower heat loss and boiler room reconstruction.
92,429.00 30

149.00

4,621.45 download icon 1

Slovenská Ľupča circuit

Reduction of energy intensity of the heat production and distribution as well as the reduction of the consumption of natural gas, fuel oil and lignite, which were used to produce heat.
50,000.00 64 207.79 3,620.62 download icon 1

Printing machine replacement

Reduction of energy intensity in printing company by replacing an old printing machine by a new one with larger printing capacity, higher printing speed and lower energy consumption.

2,260,000.00 204 771.00 113,000.00 download icon 1

Construction of boilers rooms

Reduction of natural gas consumption by installing six new high efficiency boilers.
261,401.02 152 750.60 13,070.05 download icon 1

ŽSR Eastern boiler houses

Replacement of heat sources in east area rail stations.

451,500.00 535 1,245.43 31,988.04 download icon 1

ŽSR Central boiler houses

Replacement of heat sources in central area rail stations.
532,000.00 574 951.45 33,527.22 download icon 1

Aquapark and wellness centre Púchov

Installation of PV solar power plant.

138,000.00 34 116.62 6,900.00 download icon 1

ŽSR Western boiler houses

Replacement of heat sources in western area rail stations.
398,000.00 199 648.60 19,986.60 download icon 1

Renovation of production building in Hnúšťa

The project has done some alterations of the building construction for the purpose of new technology such as: building envelope renovation, construction of a new boiler room and related heating system renovation, electricity wiring and lighting renovation and ventilation equipment installation.

894,000.00 112 761.00 44,700.00 download icon 1

Replacement of original windows and building thermal insulation

The project has replaced the thermal envelope and the original windows of 4 buildings: Spa house "Milan", the building "Balneoterapia", Catering establishment and Connection corridor.
340,000.00 117 590.05 17,000.00 download icon 1

Heat distribution pipes replacement – Revúca “Sever 2"

The project has replaced 3,356 meters of the old, poorly insulated heat distribution pipes with the new pre-insulated pipes with lower heat losses. In total 2,752 (2 x 1,376 m) meters of new pre-insulated pipes were used reducing 459 MWh/year of heat losses.

570,841.00 346 458.00 28,542.05 download icon 1

Replacement of heat sources and distribution pipelines in Banská Bystrica

The project has improved the efficiency of heat production and deliver by the creation a new connection of apartment buildings in Uhlisko by the reconstruction of natural gas boilers house at Uhlisko, at Diecézne centrum and at Wolkerova, the reconstruction of "Horná" circuit and the reconstruction of pipelines in Podháj and in Estate Heat Exchanger Station.
900,000.00 379 2,152.00 45,000.00 download icon 1

Gas boilers replacement in elementary school and in NURCH

The project has replaced the old gas boilers with new condensing boilers in the Elementary school in Trhová Hradská and in the National Institute of Rheumatological Diseases (NURCH) in Piešťany. The new condensing boilers achieve higher energy efficiency and better regulation.

270,500.00 83 423.60 13,525.00 download icon 1

Gas boilers replacement in the school Dr. Milana Hodžu

The project has replaced the old gas boilers with new condensing boilers in the Elementary school Dr.Milana Hodžu, in Bratislava. The new condensing boilers achieve higher energy efficiency and better regulation.
50,000.00 12 62.00 2,500.00 download icon 1

Improvement of insulation and windows in Liptovský Mikuláš

The project has improved basement ceiling insulation, external walls insulation, ceiling of unheated attic insulation and it has replaced both original and staircase windows.

34,525.00 2 13.89 5,179.00 download icon 1

Improvement of insulation, windows and HVAC in Liptovský Mikuláš

The project has improved external walls insulation, it has replaced original windows and it has improved the hydraulic regulation of the internal distribution of the existing heating system.
100,000.00 34 173.67 15,000.00 download icon 1

Reconstruction of quenching furnaces, cooling and reconstruction of lighting in the production hall

The project involves the reconstruction of quenching furnaces improving energy performance as well as reducing maintenance costs. It also has replaced the original lights in the production hall with 114 new LED lights, saving more energy.

176,260.00 114 416.72 8,813.00 download icon 1

Replacement of lighting in the N002 production / reconstruction hall in ŽOS Trnava

The project has installed  completely new lighting system utilising LED-based light sources in the N002 hall, which will bring significant electricity savings as well as compliance with hygiene standards regarding lighting intensity. Furthermore, the whole lighting has intelligent control implemented, adjusting optimal lighting intensity according to the levels of natural ambient light, achieving further savings.
582,136.00 221 755.50 29,106.80 download icon 1

Reconstruction of the heat sources with heat pumps, SPA Vyšné Ružbachy

The project has replaced old gas boilers with new heat pumps that use the geothermal spring available on site, in three different zones of the Spa Vyšné Ružbachy (Swiss Houses, Balneoterapia and The Grand Hotel Strand).

303,893.00 302 1,769.55 17,078.84 download icon 1

New heat source (biomass) and replacement of underground heat delivery pipes

The project has replaced the old poor-insulated heat distribution pipe of CHS by new preinsulated pipes with low heat loss and it has made a reconstruction in the boiler room, replacing the old natural gas boilers with new biomass boilers. installed  completely new lighting system utilising LED-based light sources in the N002 hall, which will bring significant electricity savings as well as compliance with hygiene standards regarding lighting intensity. Furthermore, the whole lighting has intelligent control implemented, adjusting optimal lighting intensity according to the levels of natural ambient light, achieving further savings.
1,500,000.00

2,422

1,393.00 137,017.93 download icon 1

Biomass DH project in Medzilaborce

The project has installed a new biomass boiler house and it has improved the heating system by installing Compact Heat Exchanger Stations (CHES) in buildings.

1,600,000.00 1,520 -613.70 85,989.79 download icon 1

Improvement of insulation, windows and balancing the heating system in Liptovský Mikuláš

The project has improved basement ceiling insulation, insulation cladding, flat roof insulation replaced original metal windows and balanced heating system in a residential building.
62,253.00 15 57.01 9,337.95 download icon 1

Replacement of diesel trucks with diesel/LPG engine trucks

The project has replaced 8 truck tractors having diesel engine, with new units, having combined fuel engines (diesel and Liquefied Petroleum Gas - LPG) meeting EURO VI emission standard. The new trucks have lower overall average fuel consumption and these vehicles are operated in mixed mode (28% LPG and 72% diesel).

611,280.00 68 134.79 30,564.00 download icon 1

Improvement of a residential building in Veterná Poruba

The project has improved basement ceiling insulation and external wall insulation in a residential building, saving pieces of wood and electricity.
42,300.00 1 26.81 6,345.00 download icon 1

Replacement of heat sources in residential houses and in social services home

The project has replaced heat sources to improve heat production systems in two residential houses and in a social services home. The project replaced the old natural gas boilers with new natural gas boilers with higher efficiency.

200,000.00 13 72.92 10,000.00 download icon 1

Replacement of heat sources in Banská Bystrica

The project has replaced heat sources to improve heat production systems in two sport centers buildings in DUKLA, in one office building in Bratislava. The project replaced the old natural gas boilers with new natural gas boilers with higher efficiency.
368,000.00 49 248.77 18,400.00 download icon 1

Improvement of a residential building in Pod Slivskou

The project has improved basement ceiling insulation, exterior wall insulation, loggia insulation and balanced heating system in a residential building.

350,000.00 58 210.57 52,500.00 download icon 1

Reconstruction of energy sources and distribution network in Hospital and Health centre

The project has installed new decentralized heat sources based on hot water and new valves and thermostatic heads on the local heaters. It has also replaced an old steam heat in the central ventilation system of the Hospital and Health Centre Dunajská Streda.
800,000.00 718 3,577.3 40,618.86 download icon 1

Replacement of heat sources in Košice-Šaca, Sečovce and Bratislava

The project has improved the heat production system in Residential house and Hydro-meliorations office/research facility by replacing old natural gas boilers. This project has lead to the improvement of the buildings energy performance as well as to the maintenance costs reduction.

266,000.00 239 215.10 18,640.16 download icon 1

Improvement of a residential building in Dubnica nad Váhom

The project has improved exterior wall insulation, basement ceiling insulation and the insulation of the ceiling of the top floor.
114,000.00 18 92.03 17,100.00 download icon 1

Improvement of a residential building in Trenčín

The project has improved exterior wall insulation, basement ceiling insulation and it has also replaced original steel windows.

94,920.19 13 66.18 14,238.03 download icon 1

Improvement of a residential building in Nemšová

The project has improved exterior wall insulation, basement ceiling insulation, it has also replaced original wood windows and the heating system has been balanced.
69,726.52 14 68.09 10,458.98 download icon 1

Improvement of a residential building in Dubnica nad Váhom

The project has improved exterior wall insulation, ceiling insulation, it has also replaced original entrance door and the heating system has been balanced.

90,000.00 14 76.62 13,500.00 download icon 1

Improvement of a residential building in Liptovský Mikuláš

The project has improved exterior wall insulation, basement ceiling insulation, roof insulation, it has also replaced original wood windows and the heating system has been balanced.
45,000.00 9 34.27 6,750.00 download icon 1

Improvement of a residential building in Spišská Belá

The project has improved exterior wall insulation and basement ceiling insulation.

59,999.98 22 111.23 9,000.00 download icon 1

Improvement of a residential building in Banská Bystrica

The project has improved exterior wall insulation, ceiling insulation, basement ceiling insulation, roof insulation, it has also replaced original doors and windows and a new heating system has been installed.
500,000.00 122 450.29 75,000.00 download icon 1

Improvement of a residential building in Očová

The project has improved exterior wall insulation, ceiling insulation, it has also replaced stairway windows and entrance doors and the heating system has been adjusted, including the installation of thermostatic valves.

100,000.00 19 71.41 15,000.00 download icon 1

Improvement of a residential building in Pivovarská, Ružomberok

The project has improved exterior wall insulation, flat roof thermal insulation, basement ceiling thermal insulation and the heating system has been adjusted.

100,000.00 17 64.95 15,000.00 download icon 1

Improvement of a residential building at Lesná street in Ružomberok

The project has improved exterior wall insulation, flat roof thermal insulation, basement ceiling thermal insulation and the heating system has been adjusted.

200,000.00 35 126.37 30,000.00 download icon 1

Improvement of a residential building in Jablonica

The project has improved exterior wall insulation, ceiling insulation, it has also replaced original wood and metal windows and doors and the heating system has been adjusted.

81,480.00 10 52.53 12,222.00 download icon 1

Improvement of a residential building at Scota Viatora

The project has improved exterior wall insulation, ceiling insulation, it has also improved top ceiling thermal insulation and replaced windows in common premises.

101,690.00 7 64.80 15,253.50 download icon 1

Reconstruction of public lighting in five municipalities in southern Slovakia

The project  has reconstructed the entire public lighting, excluding column and wiring, in each municipality.

93,938.19 24 89.54 4,696.91 download icon 1

Refurbishment of a compressor station in SLOVMAG, a.s. (Inc.)

The project  has installed a new compressor station with higher air production efficiency and a better control flexibility regarding the specific operation requirements in SLOVMAG, a.s. (Inc.).

104,274.00 52 178.54 5,213.70 download icon 1

Reconstruction of heat source for multifunctional building in Vysoké Tatry

The project has replaced the old natural gas boilers with heat pump (air/water technology) and new condensing boilers (as peak energy source) in the multifunctional object situated in Vysoke Tatry – Starý Smokovec.

149,606.00 25 139.10 7,480.30 download icon 1

EPC projects of lighting in three companies in western Slovakia

The project has replaced lighting with new LED technology in the production areas of the following companies: Strümsfs s.r.o., Kerkosand spol. s.r.o. and COOP VOZ, a.s.

117,479.76 35 124.99 5,873.99 download icon 1

Improvement of residential buildings in Vlachy

The project has improved exterior wall insulation, roof thermal insulation, exchanged glazed steel staircase and it has replaced the original steel windows.

59,000.00 3 17,097.00 8,850.00 download icon 1

Improvement of residential buildings in Jablonica

The project has improved basement ceiling insulation, exterior wall insulation, roof insulation, it has also replace the original windows and doors with double or triple glazing and the heating system has been adjusted.

128,853.00 13 67.43 19,327.96 download icon 1

Improvement of residential buildings in Ružomberok

The project has improved basement ceiling insulation, exterior wall insulation, ceiling below the attic insulation and roof cover replacement, it has also replace the stairway glazed wall, replace and insulate the DHW pipelines and the heating system has been refurbished completely.

101,634.00 1 43.32 15,245.10 download icon 1

Reconstruction of public lighting in Veľký Kýr.

The project has replaced lighting with new LED technology in Veľký Kýr.

116,473.95 20 69.89 5,823.70 download icon 1

Reconstruction of public lighting in Bernolákovo

The project has replaced lighting with new LED technology in Bernolákovo.

229,290.00 78 268.23 11,464.50 download icon 1

EPC projects in the Elementary school in Drotárska street (Bratislava) and in the Community centre Dunajská Streda

The project has replaced the old gas boilers with new condensing boilers, some lamps and windows in the Elementary school in Drotárska street (Bratislava) and the old gas boilers with new condensing boilers in the Community Centre Dunajská Streda.

415,000.00 131 652.90 20,750.00 download icon 1

Decentralization of the heating system and replacement of DHW preparation equipment in the complex of Žilinská Regionálna Železnica (ZRZ)

The project has decentralized the heat source and the supply system within the complex of Žilinská Regionálna Železnica (ZRZ) as well as replaced the DHW preparation technology (primary energy / fuel).

252,000.00 83 363.27 12,600.00 download icon 1

Improvement of a residential building in Vihorlatská č.12 (Bratislava)

The project has improved exterior wall insulation and the insulation of the flat roof and the basement ceiling. The windows has been replaced and the heating system has been balanced.

60,000.00 12 54.43 9,000.00 download icon 1

Improvement of a residential building in Liptovský Peter č.254

The project has improved exterior wall insulation and the insulation of the flat roof and the basement ceiling. The windows has been replaced and the heating system has been balanced.

82,273.80 8 40.01 12,341.07 download icon 1

Improvement of a residential building in Horný rad 541

The project has improved exterior wall insulation and the insulation of the flat roof. The windows and the entrance door has been replaced and the heating system has been balanced.

60,193.88 3 41.23 9,029.08 download icon 1

Improvement of a residential building in BD Športová 1547/1

The project has improved exterior wall insulation, basement ceiling insulation, flat roof insulation, it has replaced the original iron windows and has also balanced the heating system.

126,520.47 1 61.64 18,978.07 download icon 1

Improvement of a residential building in Róberta Dúbravca 1514/1

The project has improved exterior wall insulation, basement ceiling insulation, flat roof insulation and ceiling of unheated attic insulation. It has also replace the original doors.

121,124.80 21 77.09 18,186.12 download icon 1

Improvement of a residential building in Tatranská cesta 164/56

The project has improved exterior wall insulation and the insulation of flat roof and the windows has been replaced.

77,005.00 1 48.44 11,550.75 download icon 1

Improvement of a residential building in Liptovský Peter č.255

The project has improved basement ceiling insulation, exterior wall insulation, insulation of basement ceiling, insulation of flat roof and the heating system has been adjusted.

63,336.49 8 38.90 9,500.47 download icon 1

Improvement of a residential building in Liptovský Peter č.253

The project has improved basement ceiling insulation, exterior wall insulation, Insulation of ceiling below non-heated attic and the heating system has been adjusted.

95,056.80 8 39.44 14,258.52 download icon 1

Improvement of a residential building in Lesná č. 15,16,17

The project has improved basement ceiling insulation, exterior wall insulation, and the heating system has been adjusted.

199,988.00 21 96.67 29,998.20
download icon 1

EPC projects of public lighting in nine municipalities in southern Slovakia

The project  has reconstructed the public lighting in the following municipalities: Nenince, Trebušovce, Sečianky, Husiná, Vlkas, Chrastince, Belá, Čajkov, Ondrejovce

112,195.04 39 145.85 5,609.75 download icon 1

Replacement of the heat sources to improve heat production systems in particular buildings; replacement of doors and windows of the canteen building

The project has improved the heat production system in 5 buildings. The school canteen building had been also equipped with new doors and windows.

292,000.00 15 293.94 14,600.00 download icon 1
TOTAL 21,046,782.19 10,401 43,658.01   1,465,597.92